ODISHA GOVT PROHIBITS STRIKES IN POWER SECTOR
Home Department Order No. 4122/C Dated 07.11.2026
Issuing AuthorityHome (Special Section) Dept, Odisha
Order No.4122/C
Date of Issue07 November 2026
Effective From21 November 2026
Important Notice: The Government of Odisha has extended the prohibition on strikes in services connected with the generation, transmission, and distribution of electricity for a further period of six months, with effect from 21.11.2026. This order applies to GRIDCO, OPTCL, OHPC, OPGC, TPCODL, TPNODL, TPSODL, TPWODL, and any other power generating station in the State.
Strike Status
Prohibited
For 6 Months
Effective Date
21 Nov 2026
Extends Previous Order
Companies Covered
8+
GRIDCO, OPTCL, etc.
Legal Basis
ESMA 1988
Odisha Act 9 of 1992
Key Highlights of the Order
- Extension of Prohibition: The previous order prohibiting strikes in the power sector, issued vide Order No. 1580/C dated 21.05.2026, was set to expire on 20.11.2026. This new order extends the prohibition for a further period of six months.
- Effective Date: The order shall remain in force with effect from 21.11.2026.
- Entities Covered: All establishments of GRIDCO, OPTCL, OHPC, OPGC, TPCODL, TPNODL, TPSODL, and TPWODL, as well as any other power generating station in the State.
- Reason for Extension: To ensure a peaceful industrial environment and maintain continuity in the generation and supply of power in the State.
- Legal Provision: The order is issued under sub-section (3) of Section 3 of the Odisha Essential Services (Maintenance) Act, 1988 (Odisha Act 9 of 1992).
What This Means for Power Sector Employees
- No Strikes Allowed: Employees of the covered power sector companies cannot participate in any form of strike for the next six months.
- Essential Service: Power generation, transmission, and distribution have been declared essential services, and any disruption is strictly prohibited by law.
- Legal Consequences: Any violation of this order may attract penal action under the Odisha Essential Services (Maintenance) Act, 1988.
- Continuity of Operations: The order aims to ensure uninterrupted power supply to the public and industries across the State.
Frequently Asked Questions
What is this Odisha Government order about?
The order extends the prohibition on strikes in services connected with the generation, transmission, and distribution of electricity in Odisha for a further period of six months.
When does the prohibition come into effect?
The order comes into effect from 21.11.2026 and will remain in force for six months.
Which companies are covered under this order?
The order covers all establishments of GRIDCO, OPTCL, OHPC, OPGC, TPCODL, TPNODL, TPSODL, TPWODL, and any other power generating station in the State.
Why has the Government extended this prohibition?
To ensure a peaceful industrial environment and maintain continuity in the generation and supply of power in the State, which is essential for the public and industries.
Under which law is this order issued?
The order is issued under sub-section (3) of Section 3 of the Odisha Essential Services (Maintenance) Act, 1988 (Odisha Act 9 of 1992).
What happens if an employee participates in a strike?
Any violation of this order may attract penal action under the Odisha Essential Services (Maintenance) Act, 1988.